Operation of the New Intake Building

18 December 2007

New intake building has been being operated since 18 December 2007.

The facility is completed with 2 (two) raw water channel @ 1,650 Lps, 2 (two) units of automatic fine screen, 5 (five) intake pumps - 4 units @ 600 Lps and 1 units @ 500 Lps, 5 tones overhead crane and new installed 1,000 mm raw water pipe.

To serve its electricity needs, TKCM has installed additional 1,100 kVA electricity power from PLN (state owned electricity company), including constructed new building for generator, panel and transformator.

News and Events

HANDING OVER OF THE CIKOKOL PLANT TO TKCM

Plant Overview

The Cikokol Water Treatment Plant is located on the eastern bank of the Cisadane River, in the Tangerang region of Indonesia.

Water Production Rate

The graph below shows the latest treated water production rates at the Cikokol plant (litres/sec):